Skip to main content

Policy & markets

Interconnection Queues and Where Project Value Sits

For US generation and storage projects, a queue position has become one of the more valuable assets on the balance sheet. That says something about the constraint.

December 23, 2025 · 5 min read

By Consultinghouse GWB · Capital Mobilization & Structuring practice

01

The mechanism

A generation or storage project connecting to the US grid enters a queue administered by the relevant transmission operator. Studies determine what network upgrades the connection requires and what they cost, which the project generally funds. The process runs in clusters in most regions, and its outcome determines both cost and timing.

02

Why it is congested

Far more projects enter queues than are built. Developers submit multiple sites to preserve optionality, speculative entries are cheap relative to the value of a good position, and each withdrawal forces restudy of the projects behind it. The result is a queue where study timelines run years and where withdrawal rates are high.

Reforms have been introduced in several regions — higher deposits, readiness requirements, first-ready-first-served ordering, cluster studies replacing serial ones. They are changing behaviour, unevenly.

03

What it means commercially

A queue position has value. An advanced position with completed studies and a known upgrade cost is a genuinely scarce asset, and projects are acquired substantially for it.

Upgrade cost is the risk. A study can return a network upgrade allocation that makes a project uneconomic. Until studies are complete, the project's cost is not known within a useful range.

Timing drives everything else. Offtake contracts, equipment orders, tax positions, and financing all key off an in-service date that the queue controls.

Location matters more than resource. A slightly worse resource on an uncongested part of the network frequently beats a better resource behind a constraint.

04

Development practice

  • Site with the network in mind from the first screen, not after land is secured
  • Treat the study milestones as the project's real schedule
  • Structure land options and equipment reservations with terms that survive queue delay
  • Price the withdrawal option: knowing when to leave a position is part of the discipline
  • In acquisitions, diligence the queue position as carefully as the land and the resource
05

The underlying point

The constraint on US generation build-out has shifted from capital availability and technology cost to network access. Capital is present and equipment is available. Structuring a project well now means structuring it around the interconnection process, because that is where the scarcity is.

Policy & markets

Related insights

Fund structuringMarch 3, 2026

Which Exemption: How Offering Structure Decides the Investor Base

Policy & marketsFebruary 24, 2026

State P3 Statutes and What They Permit

Capital mobilizationFebruary 17, 2026

Tax-Advantaged Capital in US Energy Financing

Back to insights